Buying off-plan in Dubai carries real risks: the project can be delayed or cancelled, the finished unit can differ from what you saw, its value at handover can be lower than your price, a bank may lend less than you planned, and resale before handover is restricted. Dubai law reduces some of these risks, through escrow accounts and registration, but does not remove them. This guide explains each risk and how to check it before you sign.
Written by Next Reality Research8 min read
Key points
Escrow protects how your payments are used under Dubai Law No. 8 of 2007 on escrow accounts. It does not promise completion on time or a future value.
If RERA cancels a project, or works never start for reasons beyond the developer, buyers are entitled to a refund of all payments under the escrow law. Getting the money back can still take time.
Banks may lend up to 50% of the property value on off-plan property, so plan for a larger share in cash.
If you stop paying, the developer may terminate and keep up to 40% of the unit price if the project is 60% or more complete, or up to 25% if works have started but are below 60%.
Most risks can be checked before you sign, using DLD's official tools and your sales and purchase agreement.
Off-plan property means buying something that does not exist yet. That brings risks a ready property does not have. Dubai’s rules reduce some of them: buyer payments go into a project escrow account, every off-plan sale must be registered with the Dubai Land Department (DLD), and the law sets out what happens if a project is cancelled. Other risks stay with you. This guide names each one and shows how to check it.
Why we publish this guide
We advise on off-plan purchases, so it would be easy to talk only about payment plans and new buildings. We think a buyer who understands the risks makes a better decision, and is more likely to be comfortable with it years later. Nothing here is meant to put you off or to push you on. It is meant to help you ask the right questions and check the answers on official sources yourself.
Delivery risk: delays and cancellations
The biggest off-plan risk is that the building is finished late, or not at all.
What the law does. Under Dubai Law No. 8 of 2007 on escrow accounts, the developer must open a dedicated escrow account for the project with a DLD-accredited escrow agent. Buyer payments go into it and are released for construction against progress. If a project is not completed, the escrow agent, after consulting DLD, must take measures to preserve buyers’ rights and see that the project is completed or buyers are refunded.
If RERA cancels a project, or works never start for reasons beyond the developer, buyers are entitled to a refund of all payments under the escrow law. Disputes about unfinished and cancelled projects go to a
special tribunal, which can also assign an unfinished project to
another developer.
What the law does not do. It does not promise completion by the date in your contract. RERA monitors progress and can give a stalled developer time to correct course before starting cancellation, and DLD says liquidation of a cancelled project can take an indefinite time. A delay can push back your rental income, your move-in date or your plan to sell.
How to manage it. Check the project in DLD's Project Status Enquiry (Mashrooi) on the DLD website and in the Dubai REST app before you book: status, completion percentage, escrow bank and developer. Read the delay and grace period clauses in your sales and purchase agreement (SPA). Build slack into any plan that depends on a handover date, and look at how the developer has delivered before, as explained in our guide on how to evaluate a developer. Our guide on delays and cancellations explains your options in more detail.
Specification risk: what you get vs what you saw
Brochures, show apartments and renders are marketing. The contract is what counts.
The risk. The finished unit can differ in layout, finishes, views or size from what you expected. Amenities shown in marketing may not be in your contract.
What the law does. Under the interim register bylaw, the developer must compensate you if your unit is more than 5% smaller than the net area in the contract, and cannot charge you for extra area unless agreed. The same bylaw lets a buyer go to court to seek termination if the developer materially deviates from the specifications agreed in the contract.
How to manage it. Make sure the SPA attaches a floor plan, the net area and a specification schedule. Keep copies of the brochure and any written promises, and ask the developer to put anything important into the contract. At handover, check the unit against these documents with a snagging checklist.
Market risk: value at handover may be lower than the price paid
Property values move. The price you agree today is fixed; the value at handover is not.
The risk. If values fall, or if many similar units in the area complete at the same time, the unit may be worth less at handover than you paid. That matters most if you plan to sell at handover or need a bank valuation to borrow.
How to manage it. Base your decision on registered transactions, not headlines or marketing. DLD Real Estate Data shows registered sales and rents. Ask yourself what happens if you need to hold the unit for longer than planned.
Financing risk: mortgage approval and LTV at completion
Many buyers fund instalments from their own money during construction and plan to borrow for the balance at completion.
The risk. A bank decides on your loan when you apply, using your circumstances and its valuation at that time. If your income changes, rules change or the valuation comes in below your price, the bank may lend less than you planned, or decline.
What the rules say. For property bought off-plan, the Central Bank of the UAE caps loan-to-value at 50% of the property value. That is a maximum, and each lender sets its own limits within it. Debt burden rules also apply.
How to manage it. Speak to a bank before you commit, not at completion. Work out how much of the price you could fund yourself if a loan were smaller than expected.
Liquidity risk: resale restrictions before handover
The risk. You cannot sell an off-plan unit whenever you like, because DLD requires the developer’s consent first. A no objection certificate (NOC) from the developer is needed to resell an off-plan unit, and the developer sets its fee. Developers may require a minimum amount to have been paid before they issue the NOC, and a buyer has to be found who will take on the remaining instalments.
How to manage it. Read the SPA’s assignment clause and ask the developer for its resale conditions in writing before you book. Assume you may need to hold the unit to completion. Our guide on selling before handover covers the process.
The risk. Off-plan payment plans spread the price over construction and sometimes beyond handover. Every instalment is a legal obligation. If you fall behind, the developer must notify DLD, which gives you notice to pay. If you still do not pay, the developer may terminate and keep up to 40% of the unit price if the project is 60% or more complete, or up to 25% if works have started but are below 60%, depending on the project’s completion percentage as certified for DLD, under Dubai Law No. 13 of 2008 on the interim real estate register, as amended in 2020.
Post-handover plans mean paying the developer while you may also be paying service charges, a mortgage or furnishing costs.
If you earn in another currency, the cost of each instalment in your own currency changes with the exchange rate.
How to manage it. List every instalment with its date and amount, and check you can meet each one from money you already have or reliable income. Add a buffer for currency movements if you are paying from abroad. Our payment plan calculator builds the schedule for you.
Ask us about a project's risks
We can go through a project's status, payment plan and contract terms with you before you book. Every consultation is free, with no obligation.
The risk. The price is not the only cost. DLD registration fees, administrative charges, mortgage costs and, after handover, annual service charges all add up. Service charges in a new building may not be known when you book.
What the law does. Service charges in jointly owned buildings must be approved by RERA, and each owner pays a share based on unit area. You can look up approved rates for existing projects in the DLD / RERA Service Charge Index.
How to manage it. Ask the developer for the expected service charge budget and compare similar completed buildings in the index. List every fee before you commit, not only the price.
Regulatory and rental risk: holiday home rules, community rules
The risk. If you plan to let the unit short term, you need permission. A DET (formerly DTCM) licence and a holiday home permit are required. The activity is only allowed in areas the tourism authority permits. Building and community rules can also limit letting, alterations, pets or use. Rules can change after you buy.
How to manage it. Check that your SPA and the building rules do not prevent the use you plan. Read the permit rules on the official source before you buy, not after. Model your numbers on long-term letting too, so your plan still works if short-term letting is not possible.
The risk. Dealing with an unlicensed party, or paying into the wrong account, can cost you money that the escrow rules would otherwise protect.
What the rules say. Three rules apply:
Brokers must be licensed and entered in the DLD Real Estate Brokers Register; registration number must appear in all correspondence.
Every real estate advert needs a Trakheesi permit, and the permit number and QR code must appear on the advert.
Brokers must pay off-plan buyer money straight into the project escrow account, without deducting commission.
How to manage it. Check the broker and the brokerage on DLD’s licensed broker and licensed brokerage searches, and the developer on DLD’s licensed developer list. Make every off-plan payment to the project escrow account shown for the project in DLD's Project Status Enquiry (Mashrooi) on the DLD website and in the Dubai REST app. Treat any request to use another account as a reason to stop and check. Our guide on verifying a project and broker walks through each search.
A risk checklist before you sign
Risk
How to check
Where
Project not registered or stalled
Search the project; note status, completion and escrow bank
Projects can be delayed, plans can change and values can fall as well as rise. Read the agreement, check the project's registration and escrow account, and commit only what you can afford.
This page is general information, not legal, tax, immigration or financial advice. Rules and fees are set by the authorities and can change. Confirm the details with the authority or a licensed adviser before you act. Read our disclaimer.
Frequently asked questions
Is off-plan property in Dubai risky?
Yes, every off-plan purchase carries risk. Dubai has rules that reduce some of it: payments go into a project escrow account, sales are registered with DLD, and there is a legal route if RERA cancels a project. Delays, value changes, financing gaps and resale limits remain. Check each one before you sign.
What happens if the developer delays handover?
Your sales and purchase agreement sets the expected completion date, any grace period and any remedy for delay, so start there. You can track completion in DLD's Project Status Enquiry. For a serious delay, DLD can mediate but cannot cancel your contract; disputes go to the courts or, for unfinished projects, Dubai's special tribunal.
Can off-plan prices fall before completion?
Yes. The value of a unit at handover can be lower than the price you agreed, and nobody can promise otherwise. If you plan to sell before or at handover, or to borrow against the unit, a lower value affects you directly. Check recent registered sales in DLD's official data rather than relying on headlines.
How do I reduce risk when buying off-plan?
Verify the project and escrow account in DLD's Project Status Enquiry, check the developer and broker are licensed, read the sales and purchase agreement in full, pay only into the escrow account, budget for every instalment and fee, and plan your finance at completion. Our checklist at the end of this guide lists where to check each point.
Sources
Official sources used on this page. Each was checked on the date shown.
In Dubai, buyers' payments for off-plan property go into a separate escrow account for each project, held by a bank or financial institution accredited by DLD. The money can be used only for building that project, is released as construction stages are verified, and cannot be attached by the developer's creditors. Escrow lowers the risk of losing your payments, but it does not protect against delay, design changes or a fall in value.
You can check an off-plan project, its developer, the broker and the advert yourself on the Dubai Land Department's official services. Search the project in DLD's Project Status Enquiry (Mashrooi), confirm the developer and brokerage are licensed, check the broker in the licensed broker list, and look for the advertising permit number and QR code. This guide shows each check, what to do if something does not match, and how to verify us.
A delayed off-plan project is still going ahead, and your rights depend mainly on your sales and purchase agreement. A cancelled project is different: if RERA cancels it, Dubai law requires buyers' payments to be refunded through the escrow system, and disputes go to a special tribunal. This guide explains both situations, how to track progress on DLD's official tools, what DLD can and cannot do, and practical steps if your project is late.