What Happens If an Off-Plan Project Is Delayed or Cancelled

A delayed off-plan project is still going ahead, and your rights depend mainly on your sales and purchase agreement. A cancelled project is different: if RERA cancels it, Dubai law requires buyers' payments to be refunded through the escrow system, and disputes go to a special tribunal. This guide explains both situations, how to track progress on DLD's official tools, what DLD can and cannot do, and practical steps if your project is late.

Key points

  • A delay is governed mainly by your SPA: the completion date, any grace period and any remedy it sets.
  • If RERA cancels a project, or works never start for reasons beyond the developer, buyers are entitled to a refund of all payments under the escrow law.
  • Buyer payments sit in a project escrow account under Dubai Law No. 8 of 2007 on escrow accounts, which is what makes a refund possible.
  • You can track completion in DLD's Project Status Enquiry (Mashrooi) on the DLD website and in the Dubai REST app.
  • DLD can mediate but cannot cancel your contract at your request; contract disputes go to the courts.

If your off-plan project is late, your rights come mainly from your sales and purchase agreement (SPA). If the project is cancelled by RERA, Dubai law steps in: buyers are entitled to a refund of their payments through the escrow system, and a special tribunal handles disputes and liquidation. This guide explains the difference, where to check progress, and what you can do.

Delay vs cancellation: different situations

A delay means the project is still going ahead but will finish later than the date in your contract. Your contract stays in force, your instalments linked to construction milestones fall due as those milestones are reached, and the developer still owes you a finished unit.

A stalled project is one where work has stopped or is moving very slowly. DLD says RERA monitors construction progress and, where a project is stalled or progress is minimal, contacts the developer and gives it time to correct the position. If the developer does not, and there is no justification, RERA can start cancellation.

A cancellation is a formal decision by RERA, based on a reasoned technical report, that the project will not go ahead with that developer. The implementing bylaw of Dubai Law No. 13 of 2008 on the interim real estate register, as amended in 2020 lists the grounds. They include a developer failing to start work without valid justification, escrow law offences, no genuine intention to build, gross negligence and bankruptcy. A developer can file a grievance against the decision within a short deadline.

Some causes count as beyond the developer’s control under the bylaw, such as the land being expropriated or a government entity suspending the project for re-planning.

What your SPA says about delays

Read these clauses before you book, and again if your project runs late:

  • Completion date. Is it a fixed date, an estimated date, or a date tied to an event?
  • Grace period. Does the SPA allow the developer extra time beyond the completion date before any remedy applies?
  • Delay remedy. Does the SPA set compensation, a right to terminate, or nothing?
  • Payment schedule. Are instalments tied to construction milestones or to calendar dates? DLD notes that payment schedules are based on completion rates, and that a buyer receiving a payment request is entitled to know the current completion percentage, through a letter from the project consultant.
  • Force majeure. What events excuse the developer, and how is the buyer told?

The Dubai laws cited in this guide do not set a general compensation rate for late handover. Whether you can claim compensation depends on your contract and, if disputed, on a court. Our SPA checklist shows what to look for in each clause.

How to track progress

Use DLD's Project Status Enquiry (Mashrooi) on the DLD website and in the Dubai REST app. Search by project name or number and note:

  • the project status
  • the completion percentage
  • the developer and escrow bank
  • inspection details

the Dubai REST app also shows payments due on your unit and lets you follow projects you have invested in.

DLD explains that RERA periodically asks developers to update technical data such as the expected completion date and completion rate, so the figure you see reflects the latest technical report. If you need more detail, DLD says a buyer can ask for a report on completion prepared by RERA’s technical auditor, for a fee set by RERA.

When RERA cancels a project: escrow and refunds under the law

The core rule is in Article 11 of the interim register law, as replaced in 2020. If RERA cancels a project, or works never start for reasons beyond the developer, buyers are entitled to a refund of all payments under the escrow law.

The implementing bylaw sets out how this works:

  1. RERA issues a technical report stating the reasons, and notifies the developer.
  2. RERA appoints a certified auditor, at the developer’s expense, to check the amounts paid by buyers, the amounts in the escrow account and what has been spent.
  3. RERA asks the escrow agent (or the developer, for any payments made outside escrow) to refund the amounts to the people entitled to them, within a short deadline set in the bylaw.
  4. If the escrow account does not hold enough, the developer must refund the difference within a further deadline, which RERA can extend for valid reasons.
  5. If the developer does not pay, RERA must act to protect buyers, including referring the matter to the courts.

Separately, the escrow law requires an escrow agent, where a project is not completed, to take the measures needed, after consulting DLD, to see that the project is completed or buyers are refunded.

What the law does not promise

The law says what must be refunded and by whom. It does not promise that the escrow account will hold enough, or that the process will be quick. DLD says the time needed to liquidate a cancelled project is indefinite and depends on documents, funds and eligible persons being available. Refunds of payments made outside the escrow account depend on the developer paying them.

The special tribunal for unfinished and cancelled projects

Decree No. 33 of 2020 set up the Special Tribunal for Unfinished and Cancelled Real Property Projects, based at DLD. It has jurisdiction over claims about unfinished projects (where construction started but was suspended) and cancelled projects. Its powers include:

  • deciding claims and applications about unfinished and cancelled projects
  • assigning an unfinished project referred by RERA to another developer to complete
  • liquidating cancelled projects and settling buyers’ rights
  • appointing auditors and ordering the escrow agent or developer to refund amounts
  • proposing mediation between the parties

Other Dubai courts may not hear claims that fall within the tribunal’s jurisdiction. The decree does not apply to projects within the Dubai International Financial Centre.

Where complaints and disputes go

DLD’s role is narrower than many buyers expect.

  • DLD cannot cancel your contract. DLD states that it does not have the authority to terminate a contract between a developer and a buyer at the buyer’s request. Its role is limited to reconciling the parties.
  • Contract disputes go to the courts. Claims about compensation, refunds or the contract itself are decided by the courts, not by a complaint.
  • Complaints about a licensed company. You can take a complaint about a licensed real estate company to the relevant Dubai authorities.
  • If the developer will not register your sale. DLD says a buyer can apply to its Real Estate Registration Assurance section, with supporting documents, if a developer refuses or delays registering the sale contract.

The bylaw also lets a buyer go to court to seek termination where, for example, the developer materially deviates from the agreed specifications, refuses without valid reason to deliver the final sale agreement, or declines to link payments to the construction milestones proposed by RERA.

Practical steps if your project is late

  1. Check the official record. Look up the project in DLD’s Project Status Enquiry and save a copy of what it shows, with the date.
  2. Reread your SPA. Note the completion date, grace period, delay remedy and payment terms.
  3. Ask the developer in writing for the expected completion date, the reason for the delay and the consultant’s completion report behind any payment request.
  4. Keep paying what is properly due. Stopping payments can trigger the default process under the interim register law, where the developer may terminate and keep up to 40% of the unit price if the project is 60% or more complete, or up to 25% if works have started but are below 60%. Take advice before withholding anything.
  5. Pay only into the escrow account. Never agree to pay instalments anywhere else, even to “speed things up”.
  6. Keep records of every payment, letter and email.
  7. Take legal advice if the delay is long, the developer stops responding, or you are considering termination. A lawyer can tell you whether the courts or the special tribunal apply.

Off-plan carries risk

Projects can be delayed, plans can change and values can fall as well as rise. Read the agreement, check the project's registration and escrow account, and commit only what you can afford.

Risks of Buying Off-Plan

Talk to an advisor

We can check your project's official status with you and help you prepare questions for the developer. Every consultation is free, with no obligation.

Free Consultation

Our guide to escrow accounts explains how your payments are held, and the risks of buying off-plan covers delivery risk alongside the others. Before your next purchase, our developer due diligence service can help you check a developer’s record, and our off-plan guide covers the full process.

General information only

This page is general information, not legal, tax, immigration or financial advice. Rules and fees are set by the authorities and can change. Confirm the details with the authority or a licensed adviser before you act. Read our disclaimer.

Frequently asked questions

Do I get compensation if my off-plan project is delayed?

Only if your contract or a court says so. The Dubai laws cited in this guide do not set a general compensation rate for late handover. Check your sales and purchase agreement for the completion date, grace period and any delay remedy. For a serious delay, take legal advice; a court can consider termination where the developer has broken the contract.

What happens to my money if a project is cancelled?

If RERA cancels a project by a final decision, the developer must refund all buyer payments under the escrow law. RERA asks the escrow agent to refund the amounts in the account, and if they are not enough, the developer must pay the rest within a deadline set in the bylaw. Unpaid amounts are referred to the courts or the special tribunal.

Can DLD cancel my contract with the developer?

No. DLD states that it does not have the authority to terminate a contract between a developer and a buyer at the buyer's request. Its role is limited to trying to reconcile the parties. To end the contract, a buyer has to go to the competent court or, for unfinished and cancelled projects, the special tribunal.

How do I check whether my project is on schedule?

Search the project in DLD's Project Status Enquiry, or Mashrooi in the Dubai REST app. It shows the project status, completion percentage, developer and escrow bank. Compare the completion percentage over time and against the payment milestones in your contract. You can also ask the developer for the consultant's report behind each payment request.

Sources

Official sources used on this page. Each was checked on the date shown.

Show 8 SourcesHide Sources
  1. Law No. (8) of 2007 Concerning Escrow Accounts for Real Estate Development in the Emirate of Dubai, Dubai Legal Portal, checked 16 October 2026
  2. Law No. (13) of 2008 Regulating the Interim Property Register in the Emirate of Dubai, Dubai Legal Portal, checked 16 October 2026
  3. Law No. (19) of 2020 Amending Law No. (13) of 2008 Regulating the Interim Real Property Register in the Emirate of Dubai, Dubai Legal Portal, checked 16 October 2026
  4. Executive Council Resolution No. (6) of 2010 Approving the Implementing Bylaw of Law No. (13) of 2008, Dubai Legal Portal, checked 16 October 2026
  5. Decree No. (33) of 2020 Concerning the Special Tribunal for Unfinished and Cancelled Real Property Projects, Dubai Legal Portal, checked 16 October 2026
  6. Project Status Enquiry (Mashrooi), Dubai Land Department, checked 16 October 2026
  7. Frequently Asked Questions, Dubai Land Department, checked 16 October 2026
  8. Dubai REST app, Dubai Land Department, checked 15 October 2026
  • 8 min read

    Escrow Accounts and Buyer Protection in Dubai

    In Dubai, buyers' payments for off-plan property go into a separate escrow account for each project, held by a bank or financial institution accredited by DLD. The money can be used only for building that project, is released as construction stages are verified, and cannot be attached by the developer's creditors. Escrow lowers the risk of losing your payments, but it does not protect against delay, design changes or a fall in value.

  • 8 min read

    What to Check in an Off-Plan Sales and Purchase Agreement

    The sales and purchase agreement (SPA) is the contract that sets your rights in an off-plan purchase, so read all of it before you sign. It decides what you are buying, what you pay and when, how late the developer can be, what may change, and what happens on default. Before you sign, check the unit and its net area, the payment schedule and escrow account, the completion and delay clauses, the specification, the default and resale terms, service charges, handover and the dispute route.

  • 8 min read

    Risks of Buying Off-Plan and How to Manage Them

    Buying off-plan in Dubai carries real risks: the project can be delayed or cancelled, the finished unit can differ from what you saw, its value at handover can be lower than your price, a bank may lend less than you planned, and resale before handover is restricted. Dubai law reduces some of these risks, through escrow accounts and registration, but does not remove them. This guide explains each risk and how to check it before you sign.

Book a free consultation

Every consultation is free, with no obligation. Our team speaks 7 languages.

Free Consultation

Every consultation is free, with no obligation.

What is your main goal?
Your budget and timing
Budget
When would you like to buy?
How can we reach you?

Choose your country, then type your number.

Preferred contact method

By sending this enquiry, you agree that Next Reality may contact you about it.

We use your details as described in our privacy policy.