To buy off-plan property in Dubai, you verify the project and developer on DLD’s official services, reserve a unit, sign a sales and purchase agreement (SPA) with the developer, have the sale registered in the interim register (Oqood), and pay instalments into the project’s escrow account. At completion you pay the balance, inspect the unit, take the keys and receive the title deed. The ten steps below explain what happens at each stage and what to check.
If you are new to off-plan, start with our overview of off-plan in Dubai, then come back to this guide when you are ready to act.
Before you start: goals, budget, financing, timeline
Settle four things before the first payment. A plan that only works if everything goes right leaves no room for a delay or a smaller mortgage.
- Goal. Will you live in the unit, let it, or hold it for resale? Each goal points to different areas, unit types and payment plans.
- Budget. Count the whole cost, not just the price: registration fees, any administration charges, the mortgage costs at completion if you borrow, and service charges once you own the unit. Our purchase cost calculator adds these up from your own inputs.
- Financing. Banks may lend no more than 50% of the property value on off-plan property, and each bank sets its own criteria. Decide whether you will pay from your own funds, use a mortgage at completion, or both, and what you will do if the loan offered is smaller.
- Timeline. Construction takes time and can run late. Your plan should still work if handover is delayed.
Write the answers down. A one-page plan with your goal, the most you will spend in total, how each instalment will be funded and your fallback if the mortgage is smaller makes every later decision easier, and it gives you a fixed point to come back to when a sales conversation moves fast.
Step 1: Shortlist projects and verify them
Before you spend time on a sales conversation, check that the project and the people selling it are who they say they are. Each of these checks uses a public DLD service, so you can do them yourself and repeat them at any point.
- The project. Search for it in DLD's Project Status Enquiry (Mashrooi) on the DLD website and in the Dubai REST app. The results show the project number, status, completion, developer, escrow bank and inspection details.
- The developer. Check the name against DLD’s list of licensed developers. Under the escrow law, no developer may sell off-plan unless it is entered in DLD’s developer register and licensed.
- The advert. Every real estate advert needs a Trakheesi permit, and the permit number and QR code must appear on the advert. An advert without them is a reason to ask questions.
- The broker. Brokers must be licensed and entered in the DLD Real Estate Brokers Register; registration number must appear in all correspondence. Check the broker’s name in DLD’s licensed brokers service.
RERA’s own guidance sets out what a broker must confirm before marketing an off-plan project. Brokers marketing off-plan must confirm RERA project registration, an escrow account and a developer marketing contract. The guidance names the Dubai REST app’s Mashrooi service as the way to check. Our guide on how to verify a project and broker walks through each check and what a mismatch means.
Step 2: Expression of interest and reservation
For some launches, developers invite an expression of interest (EOI) before units are formally released. For others, you go straight to a reservation or booking form. Either way, this is the step where you first commit money, so it is where care pays off.
What an EOI is and is not
An EOI is a statement that you would like to be offered a unit. It is not a sale and it gives you no ownership rights. The implementing bylaw of the interim register law says any off-plan sale made before the project is approved by the competent authorities and registered with DLD is void. At real estate exhibitions, DLD’s permit rules allow only preliminary reservations, not sales, and do not allow Dubai off-plan projects to be shown unless they are registered with DLD’s escrow account department.
Before you pay anything at this stage, ask for written answers to these questions:
- Is the payment refundable, in full or in part, and under what conditions?
- Into which account is it paid? It should be the project’s escrow account.
- How is it credited against the price if you go ahead?
- What happens if you are not offered the unit, floor or view you asked for?
- How long does the developer hold the unit for you before the booking lapses?
Step 3: Booking and the reservation agreement
Booking turns your interest in a specific unit into a commitment. You sign a reservation or booking form that names the unit, the price and the payment plan, and you pay the booking amount set by the developer.
The rule on where money goes is clear. Brokers must pay off-plan buyer money straight into the project escrow account, without deducting commission, and any agreement to the contrary is void. Pay the developer’s project escrow account, keep the receipt, and check that the account details match the escrow account number shown for the project in the Dubai REST app. A request for cash, or for payment into a personal or company account that is not the project escrow account, is a warning sign.
Read the booking form as carefully as the SPA. It often says what happens to your booking amount if you do not sign the SPA within a set time, and DLD uses the addresses in the booking form for formal notices if the SPA is not available.
Step 4: The sales and purchase agreement (SPA)
The SPA is the contract that governs your purchase until handover. When a developer opens a project’s escrow account, it must give DLD a standard sale contract, so the core terms tend to follow that form. Read it in full before you sign, and pay particular attention to:
- the unit, its net area and the plan attached to the contract;
- the price, the payment schedule and the project escrow account details;
- the completion date, any grace period and what happens if the developer is late;
- what the developer may change in the specification;
- what happens if you miss a payment;
- the conditions and costs for selling before handover;
- service charges and community rules;
- handover, defects and the dispute route.
The implementing bylaw also lists situations in which a buyer may ask the court to end the contract. They include a developer refusing without valid reason to deliver the final sale agreement, declining to link payments to the construction milestones proposed by RERA, materially departing from the agreed specifications, or handing over a unit that proves unfit for use because of material construction defects. Knowing these grounds helps you read the default and termination clauses with the right expectations.
If a clause is unclear, ask the developer to explain it in writing before you sign, and consider independent legal advice for anything that affects your money or your right to end the contract. Our SPA checklist goes through each clause and what to look for.
Step 5: Oqood registration and DLD fee
Once the SPA is signed, the developer registers the sale in the interim register through DLD’s Oqood portal. Under Dubai Law No. 13 of 2008 on the interim real estate register, as amended in 2020, an off-plan sale that is not entered in the interim register is void, and DLD requires registration within 90 days of signing the sale and purchase contract. DLD emails a provisional registration e-certificate to the purchaser when it is done.
DLD lists these fees for the registration: 4% of the sale value (2% from the seller and 2% from the buyer), an AED 10 knowledge fee and an AED 10 innovation fee, and AED 1,000 when the developer registers the sale in Oqood itself. Who pays is a separate question. Officially 2% seller and 2% buyer, but DLD says the 4% is paid according to the seller-buyer agreement. DLD has also called on developers to pass registration fees on to DLD promptly once buyers have paid them, which is one more reason to keep every receipt.
If a developer refuses or delays registering your contract, DLD’s guidance is that you can apply to its Real Estate Registration Assurance section with your supporting documents. Our guide to Oqood registration and DLD fees explains the process and the fees in detail.
Step 6: Paying instalments into escrow
From here, you pay instalments as the SPA requires. Under Dubai Law No. 8 of 2007 on escrow accounts, buyers’ payments go into an account in the project’s name, used only for building that project, and the developer’s creditors cannot attach it. DLD’s guidance explains that money is released from escrow to contractors and consultants when the escrow agent’s engineer has checked that a construction stage has been reached.
Where an instalment is linked to a stage of completion, DLD’s guidance says you are entitled to know the current completion percentage when the developer asks for payment, through a letter from the project consultant. Ask for it if it is not included.
Keep a simple record of each payment: date, amount, account paid into and receipt. If you fall behind, the law sets a process before the developer can act. The developer notifies DLD, DLD gives you a notice period to pay, and only then may the developer terminate and keep up to 40% of the unit price if the project is 60% or more complete, or up to 25% if works have started but are below 60%, depending on the certified stage of construction. If you think you may miss a payment, talk to the developer early.
Step 7: Tracking construction
You do not have to rely on the developer’s newsletters to follow progress. The Dubai REST app gives off-plan buyers project data including the percentage of completion, actual photos of the project, the escrow account number and the payments due on your unit, and you can mark a project as a favourite to follow it. You can also look a project up in DLD's Project Status Enquiry (Mashrooi) on the DLD website and in the Dubai REST app.
Use both sources together. If the developer’s updates and the official completion figure drift apart, ask the developer to explain the difference in writing. If the completion date in your SPA is approaching and progress looks slow, read the delay and grace period clauses again so you know your position.
A delay is not the same as a cancellation. A late project is still governed by your SPA, and your remedies depend on what it says about the completion date, the grace period and compensation. A cancellation is a formal decision by RERA, and the law then requires buyers’ payments to be refunded under the escrow law. DLD’s role in a contractual dispute is limited: it can try to reconcile the parties, but it does not rule on contractual claims, which go to the courts. Keep copies of every notice, payment and update so that you can show your position clearly if you ever need to.
Step 8: Completion, final payment or mortgage drawdown
When the project is finished, the developer obtains a completion certificate and asks buyers to pay what remains under their plan. If you are paying from your own funds, you pay the final instalment into the escrow account.
If you are using a mortgage, start the conversation with lenders well before completion. The bank will value the finished unit, check your income and debts, and decide how much to lend, within the Central Bank’s limits. When a sale is financed, DLD has a service for registering the sale together with the mortgage, and registering a mortgage costs 0.25% of the mortgage value, plus other fees listed by DLD. If the loan offered is smaller than you need, you have to fund the difference yourself, so build a buffer into your plan.
Step 9: Handover, snagging, title deed
Handover is when you inspect the unit and take the keys. Inspect carefully, or have a professional do it: walls, floors, doors, windows, wet areas, kitchen, electrics, air conditioning, plumbing and balcony. Record defects in writing and agree a date to re-inspect. Our handover and snagging checklist gives a room-by-room list.
Once you have met all your contractual obligations, the developer may not refuse to hand over the unit or register it in your name, including allocated facilities such as a parking space. If a developer refuses without reason, DLD may register the unit in your name. When the unit moves from the interim register to the main property register, DLD issues your title deed and charges an AED 250 title deed certificate issuance fee. In jointly owned buildings, Law No. (6) of 2019 also keeps the developer liable for repairing defective installations for a period after handover.
Step 10: After handover: occupy, lease or sell
With the title deed in your name, you decide how to use the property.
- Move in. Set up utilities and register with the building’s management for access and service charges. Owners pay annual service charges pro rata to unit area; charges need RERA approval.
- Lease. Tenancy contracts in Dubai are registered in Ejari, DLD's system for registering tenancy contracts. Check the community’s rules on leasing before you advertise, and look at the official rental index for your area rather than asking prices.
- Sell. A completed unit is sold through DLD’s sale registration service at a registration trustee office, with fees set by DLD and a no objection certificate from the developer in freehold areas.
Documents you will need at each step
| Step |
What is usually asked for |
| Reservation |
Passport copy, Emirates ID if you are a UAE resident, contact details and the booking form |
| SPA and Oqood |
Signed SPA, valid UAE ID, or a passport copy if you are not a UAE resident; for companies, the trade licence, constitutional documents and any power of attorney |
| Payments |
Receipts showing payment into the project escrow account |
| Mortgage at completion |
The lender’s own documents, plus a bank letter on the mortgage and the signed mortgage contracts for DLD registration |
| Handover |
Proof of final payment, ID, and the developer’s handover forms |
The exact list depends on the developer, the bank and whether you buy as an individual or a company. Our guide to documents you need to buy property in Dubai covers each case.
Buying from outside the UAE: what changes
You can buy off-plan in Dubai without living there, and much of the process is online. The developer files the Oqood registration through DLD’s portal and DLD emails the certificate to the purchaser. For non-residents, DLD’s Oqood service asks for a valid passport copy instead of a UAE ID.
Three things change in practice:
- Signing. If someone signs on your behalf, DLD requires a power of attorney issued outside the UAE to be legalised in the country of issue, including by the UAE embassy there, and then attested by the UAE Ministry of Foreign Affairs.
- Paying. International transfers take time and currency rates move, so plan instalments with a margin, and pay only into the project escrow account.
- Checking. You cannot drop by the site, so use the Dubai REST app to follow progress and the escrow account number.
Our guide to buying property in Dubai remotely covers powers of attorney, payments from abroad and handover when you are not in the country.
Plan your purchase with us
Every consultation is free, with no obligation.
Free Consultation